Water Supply Borsod-Abauj-Zemplen
Switzerland is contributing CHF 7.803 mio. to improve the water supply network in 11 municipalities of the subregion Borsod-Abaúd Zemplén. Additionally, a water supply network will be introduced in two settlements that are so far only partly or not at all connected to a network.
| Pays/région | Thème | Période | Budget |
|---|---|---|---|
|
Hongrie |
Protéger l’environnement
Alimentation en eau potable
|
10.11.2010
- 30.04.2017 |
CHF 7'803'000
|
- To provide the same service level (security of supply and quality) in all municipalities supplied by the water company.
- To maintain the price of water affordable for all consumers of the supplied region.
- To enable the water company to invest certain savings due to this project into the rehabilitation of the entire network even after this project is implemented.
- Construction works in 13 settlements with a total population of about 40’000 people (network rehabilitation and extension) have been completed. As a result, the water supply network in these settlements is built and has been extended in accordance with the original objectives.
- 4.7 km of new pipeline was installed and 70.5 km of asbestos cement pipeline has been replaced.
- Network water losses dropped by 94%.
- Operating costs were reduced by more than 10%.
- Hungarian National Development Agency
-
Thème transversal Le projet tient compte de l'environnement en tant que thème transversal.
Numéro de projet UX00302
| Contexte |
The water company (Borsodvíz Zrt.), a publicly owned company that owns the water infrastructure, strives to rehabilitate the most critical elements of its water supply network in 11 municipalities of the micro-regions of Abaúj-Hegyköz, Mezőcsát and Tokaj. The transportation mains, city mains and household connections suffer from early aging due to poor quality of the pipes, un-thorough execution of the mounting works and insufficient bedding of the pipes. Furthermore the deterioration is accelerated by the aggressive geological conditions. Additionally, the water company plans to introduce a water supply network in the Emőd-Adordjántanya and Sima settlements that are only partly or not at all connected to a network. |
| Objectifs |
|
| Groupes cibles |
The 13 municipalities of the subregion Borsod Abaúd-Zemplén, GW Borsodvíz Ltd., the 38'520 inhabitants as well as the 30'000 tourists. |
| Activités |
Partial replacement of the water supply network. Rebuilding of the water supply network in the settlements Sima and Emőd-Adordjántanya. |
| Résultats |
Résultats obtenus: |
| Direction/office fédéral responsable |
SECO |
| Crédit |
Contribution suisse à l'UE élargie |
| Partenaire de projet |
Partenaire contractuel Partenaire de mise en œuvre VÁTI Ltd and Borsodvíz Zrt. Water Company
|
| Budget | Phase en cours Budget de la Suisse CHF 7'803'000 Budget suisse déjà attribué CHF 7'739'131 |
| Phases du projet |
Phase 4
10.11.2010
- 31.05.2016
(Completed)
Phase 3
10.11.2010
- 30.11.2016
(Completed)
Phase 2
10.11.2010
- 31.05.2017
(Completed)
Phase 1 10.11.2010 - 30.04.2017 (Completed) |