Phase 2: Community Service Workshops (01.01.2012 - 30.06.2016)
Community Service Workshops (Probation)
The project will - on the experience already gained since 2007 - establish a community service workshop in Bucharest in partnership between VEBO Switzerland, the Foundation FPSC and the Ministry of Justice in Romania as well as set the basis for the creation of two more workshops in other cities. The project is part of the thematic fund security in Romania. Further information about this fund can be found among the additional information on the very bottom of this page.
| Paese/Regione | Tema | Periodo | Budget |
|---|---|---|---|
|
Romania |
Rafforzare la sicurezza pubblica
Ammodernamento del sistema giudiziario
|
01.07.2011
- 31.12.2014 |
CHF 133'935
|
- developing special facilities, i.e. workshops, where CS can be properly executed and supervised, in a safe environment – also for minors - and in an efficient manner
- stimulating the judges and the probation services to encourage CS, which has proved to have high benefits
- 2nd workshop in Bucharest renovated.
Decision on the locations for the next two workshop taken
- Improved quality management measures elaborated
- Altra organizzazione svizzera non profit
-
Settore in base alle categorie del Comitato di Aiuto allo sviluppo (DAC) dell'OCSE Unallocated / Unspecified
Sotto-Settore in base alle categorie del Comitato di Aiuto allo sviluppo (DAC) dell'OCSE Sectors not specified
Tipo di aiuto Contributo all'allargamento
Numero del progetto 7F08089
| Contesto |
The project’s priority sector is the Romanian judiciary in general with a focus on the execution of community service hours as an obligation imposed by the court within the Romanian Probation system. According to various studies, community service (CS) seems to be an appealing option for the judges everywhere in the world. |
| Obiettivi |
|
| Gruppi target |
Persons sentenced to community service, prison system |
| Attività |
The project activities are divided in nine components which are planned to be implemented in defined periods between July 2011 and end of 2014. This credit proposal only covers a first phase of a maximum of six months during which the first three components will be executed.
|
| Risultati |
Risultati raggiunti: The project has been completed at an operational level. |
| Direzione/Ufficio responsabile |
DSC |
| Credito |
Contributo svizzero all'allargamento dell'UE |
| Partner del progetto |
Partner contrattuale Organizzazione svizzera senza scopo di lucro Altri partner VEBO Zurich |
| Budget | Fase in corso Budget Svizzera CHF 133'935 Budget svizzero attualmente già speso CHF 133'935 |
| Fasi del progetto |
Fase 1 01.07.2011 - 31.12.2014 (Completed) |