Wastewater and Solid Waste Management Vietnam


In a context of rapid urbanisation, this project implemented by the German KfW aims at contributing to a more sustainable urban development by expanding the sewer network and build wastewater treatment plants in three secondary cities in Northern Vietnam.

Land/Region Periode Budget
Vietnam
25.10.2010 - 31.05.2027
CHF  8’673’000
Hintergrund

About a third of Vietnam's population currently lives in urban areas and it is expected that this percentage will increase to around 50% by 2040. Increasing urbanisation also causes a strong pressure on natural resources and the environment, with lacking wastewater sewage systems and treatment and unsecured dumpsites as the main causes of water pollution in the cities. Consequently, Vietnam strives to achieve connection rates of 80 - 90% of urban households to the sewerage system by 2020 and increase the operation of wastewater treatment plants in urban centres.

Ziele

By improving wastewater treatment management capacities, the overall goal of the project is to reduce environmental impacts of rapid urbanization in three provinces in Northern Vietnam.

Mittelfristige Wirkungen

The objectives are to a) improve sanitation in three provincial centres in Northern Vietnam by raising sewerage coverage and hence connection rate and by providing wastewater treatment facilities so as to meet the relevant discharge standard, b) reduce flooding through systematic spatial development planning and c) build capacity through capacity building and non-technical measures.

Verantwortliche Direktion/Bundesamt SECO
Kreditbereich Entwicklungszusammenarbeit
Budget Laufende Phase Schweizer Beitrag CHF    8’673’000 Bereits ausgegebenes Schweizer Budget CHF    0 Budget inklusive Projektpartner CHF    8’673’000
Projektphasen Phase 1 25.10.2010 - 31.05.2027   (Laufende Phase)