The NGO Block Grant aims to strengthen Romanian NGOs and to enable their active participation in policy processes as the voice of civil society as well as a service provider and to promote activities of the Civil Society Organisations tackling environmental issues, contributing to the provision of social services and allowing for strengthening their organisational capacities. The project is part of the thematic fund for Civil Society Participation in Romania.
Pays/région | Thème | Période | Budget |
---|---|---|---|
Roumanie |
Renforcer la société civile
Organisations non gouvernementales
|
15.05.2012
- 30.11.2019 |
CHF 9’900’692
|
- Small grants: minimum CHF 10’000 and maximum CHF 75’000 - with a duration of 12-18 months
- Large grants minimum CHF 75’001 and maximum CHF 250’000 - with a duration of 12 - 36 months (only for the Social Component)
- 94 projects aiming at strengthening Romanian NGOs and enabling their active participation in policy processes have been implemented. NGOs were promoted as the voice of civil society and as service provider in the field of environment, social services and strengthening organisational capacities.
- The financed projects were from 2 main Components: Social (64) and Environment (30).
- The civil society organisations contributed as important actors in development processes in Romania.
- Secteur privé suisse
- KEKconsultants consortium, Zurich
-
Type d'aide Contribution à l'élargissement
Numéro de projet 7F08040
Groupes cibles |
Romanian Civil Society including NGOs. |
Activités |
The Block Grant for NGOs is focusing on offering support in two major domains: social issues and environment protection. Two types of projects will be financed: |
Résultats |
Résultats obtenus: |
Direction/office fédéral responsable |
DDC |
Crédit |
Contribution suisse à l'UE élargie |
Partenaire de projet |
Partenaire contractuel Secteur privé |
Budget | Phase en cours Budget de la Suisse CHF 9’900’692 Budget suisse déjà attribué CHF 4’163’439 |
Phases du projet |
Phase 7
01.07.2014
- 30.09.2017
(Completed)
Phase 6
01.01.2014
- 31.12.2016
(Completed)
Phase 5
01.07.2013
- 30.06.2016
(Completed)
Phase 4
01.07.2013
- 30.06.2016
(Completed)
Phase 3
01.04.2013
- 30.04.2016
(Completed)
Phase 2 15.05.2012 - 30.11.2019 (Completed) Phase 1 01.07.2011 - 30.11.2019 (Completed) |