Financing of World Bank EDO Advisors


Switzerland leads a constituency of nine countries in the Executive Board of the World Bank Group, giving it a high level of influence in governance and decision-making. To maintain and strengthen the permanent Board seat, Switzerland finances three non-Swiss advisors to the Swiss Executive Director’s Office. Based on a four-year co-financing arrangement between SDC and SECO, SDC assumes the cost for 2023-2024.

Paese/Regione Tema Periodo Budget
Mondo
Altro
Sector not specified
01.01.2023 - 31.12.2025
CHF  1’645’400
Contesto

Switzerland represents a group of nine countries on the 25-seat Board of Directors of the World Bank Group (WBG), which is in charge of the oversight and policy decisions on WBG operations. The Swiss-led constituency employs Advisors who assist the Swiss Executive Director in his work. Not all these Advisors are financed by the WBG.

This intervention finances three Advisor positions from the constituencies’ Central Asian countries. These Advisors acquire invaluable knowledge during their tenure at the Executive Director’s Office (EDO), which increases capacity in their home countries upon their return. The EDO benefits from additional manpower in managing Board business. The contribution helps to secure the permanent seat of Switzerland in the WBG Board, a clear Swiss interest. 

Obiettivi Swiss influence within the WBG Board of Directors is ensured. 
Gruppi target EDO Advisors from Tajikistan, Kazakhstan, Uzbekistan 
Effetti a medio termine

Outcome 1: The Swiss seat at the WBG Board is maintained.

Outcome 2: The Swiss position within the WBG is strengthened thanks to the work of the EDO.

Risultati

Risultati principali attesi:  

  • Improved effectiveness and efficiency of EDO
  • Improved bilateral relationships for Switzerland with Kazakhstan and Tajikistan


Risultati fasi precedenti:   The Swiss-led constituency and the permanent seat at the WBG Board is maintained. The financed Advisors performed as expected.


Direzione/Ufficio responsabile DSC
Partner del progetto Partner contrattuale
Istituzione finanziaria internazionale
  • Banca mondiale - Banca internazionale per la ricostruzione e lo sviluppo


Coordinamento con altri progetti e attori Coordination with SECO, Swiss Federal Department of Finance and Swiss National Bank
Budget Fase in corso Budget Svizzera CHF    1’645’400 Budget svizzero attualmente già speso CHF    1’446’875 Progetto totale dalla prima fase Budget Svizzera CHF   2’912’925
Fasi del progetto Fase 4 01.01.2023 - 31.12.2025   (Fase in corso) Fase 3 01.01.2019 - 31.12.2020   (Completed) Fase 2 15.12.2014 - 31.12.2018   (Completed)